A northern Minnesota utility broke ground this week on a $900 million electric transmission project that’s expected to play a critical role in the state’s clean energy transition.

Duluth-based Minnesota Power is upgrading and expanding a 50-year old high voltage direct current (HVDC) transmission line that runs 465 miles from Center, N.D., to Solway Township, just outside Duluth.

It’s one of just two HVDC lines in Minnesota, and there are only a few across the country. They’re valuable because they transmit electricity more efficiently over long distances than more common alternating current, or AC, lines.

The project is expected to play an important role as Minnesota transitions to an energy future powered largely by renewable electricity that’s often produced in far-flung rural areas, including wind farms in the Dakotas and elsewhere around the upper Midwest.

"This line is primarily driving a lot of our clean energy investments from North Dakota, where wind is most efficient, to here in Duluth,” said Dan Gunderson, Vice President of transmission planning for the utility. “So it's really helping with Minnesota’s clean energy goals."

Utilities in Minnesota are required to produce 100 percent of their electricity from carbon-free sources such as wind and solar by 2040. Minnesota Power currently generates about 60 percent of its electricity from such clean energy sources.

The project does not entail stringing new electric transmission lines. Rather, crews are building new electric substations and converter stations at both ends of the line that will allow Minnesota Power to nearly double the amount of energy the line delivers. The stations will convert the HVDC power to AC so it can flow onto the existing electric grid.

“When they built this line, they manufactured the largest possible cable that they could in the world,” Gunderson said. “This was a record-breaking cable that was on here in the 70s, and so they built it with that future capacity in mind.”

The new converter stations will also allow electricity to flow in either direction. The project will connect to a proposed new 67-mile long power transmission line that will run between the Iron Range and this part of St. Louis County just outside Duluth that Minnesota Power is building out as an electricity transmission hub.

That proposed power line, which still needs approval from the Minnesota Public Utilities Commission, faces opposition from area residents who are fighting a controversial proposed Google hyperscale data center.

A red and white sign reading "NO! Data center" sits on a wooden fence post in a clearing under a power line.
A sign opposing a proposed Google data center in Hermantown is posted along an electric transmission line corridor off of St. Louis River Rd., near where the data center would be built. Seen Tuesday.
Dan Kraker | MPR News

The data center has been proposed for a rural corner of Hermantown adjacent to where the new electric transmission infrastructure is being built. Data centers require enormous amounts of electricity — often as much as small cities — and they are often proposed for locations near sources of large supplies of available electricity.

Planning for this transmission project began over a decade ago, long before Google proposed its data center project for the region. But the improvements the project will provide to the regional electricity grid would support the data center if it’s built, Gunderson said.

“We've always been a utility that served large customers. That's what we do,” Gunderson added. “So we know how to design systems around that, whether it be mining, natural resources or other customers. We want to have a system capable of supporting that.”

The project received $25 million in support from the state, as well as $50 million in federal funding through the bipartisan infrastructure law passed during the Biden administration.

The Trump administration revoked that funding last year as part of its broader effort to cancel $8 billion in grants that the Biden administration awarded to 16 states aimed at accelerating the green energy transition.

But the Department of Energy returned the funding earlier this year after Minnesota Power appealed. “The original grant was very much a bipartisan effort between the delegations from Minnesota and North Dakota, because we have facilities in both areas, and we just reaffirmed that in the appeal,” Gunderson said.



Source link



The morning sun shines through hazy skies

Air quality in the Twin Cities may reach unhealthy levels on Friday afternoon and evening.

The Minnesota Pollution Control Agency has issued an air quality alert for the Twin Cities metro area from noon to 9 p.m. Friday.

Unlike many air quality alerts in Minnesota in recent years, Friday’s alert does not stem from wildfire smoke in the air. Instead, it’s due to ground-level ozone created by a combination of weather conditions.

“Mostly sunny skies, warm temperatures and low humidity will provide a favorable environment for two types of pollutants (volatile organic compounds and nitrogen oxides) to react with sunlight in the air to produce ground-level ozone,” the MPCA reported.

Forecasters say air quality in the metro area may reach the orange category on Friday afternoon and evening — meaning unhealthy for sensitive groups. That includes people with asthma or other chronic breathing conditions, as well as children and the elderly.

“Unhealthy ozone can aggravate lung diseases like asthma, emphysema, and COPD. When the air quality is unhealthy, people with these conditions may experience symptoms like difficulty breathing deeply, shortness of breath, throat soreness, wheezing, coughing, or unusual fatigue,” the MPCA reported.

People in the Twin Cities — especially those in sensitive groups — may want to limit or postpone outdoor activities while the alert is in effect.

The air quality should improve after sunset Friday.

The MPCA offered tips on how people can help reduce the amount of pollutants in the air:

  • Reduce driving; carpool or use public transit when possible

  • If you need to fill your vehicle with gas or diesel, avoid filling up during the middle of the day

  • Avoid using gasoline-powered lawn and garden equipment until the alert has ended, or use battery or manual-powered equipment instead

  • Avoid backyard campfires



Source link

Recent Reviews